Inclement Weather & Lightning
Document NU-SAF-126

NU-SAF-126 — INCLEMENT WEATHER & LIGHTNING

Tier 2/3 — Procedure + Field Card · Rev DRAFT · Drafted August 2, 2026 · Owner: Field Supervisor Parent: NU-SAF-100. [Adam: confirm which §5 element this hangs under.] Register line (NU-GOV-000 §4.1): "30/30 rule. Cheap."


THE GATE

See the flash, count to the thunder. Under 30 seconds = work stops and everyone is in a cab or a truck. Nobody comes back out until 30 minutes after the LAST thunder. Every new rumble resets the clock.

Record: stop time, restart time, and reason go in the DFR the same day (§8). A weather stop with no DFR line didn't happen — and the schedule hit it caused can't be defended later.

There is no OSHA lightning standard to hide behind. Lightning deaths on outdoor crews are cited under the General Duty Clause (OSH Act §5(a)(1)), and the OSHA–NOAA fact sheet Lightning Safety When Working Outdoors (OSHA 3863) is where the 30-minute rule comes from. This page is Nova's version of it.


1. WHY THIS DOCUMENT IS SHORT

Weather kills a utility crew three ways, and all three have the same fix — stop early, write it down:

  1. Lightning. The rig is the tallest piece of metal on most sites Nova works.
  2. Water in a trench. A trench takes water two ways — it fills, or it caves. Both are covered by NU-SAF-107 and summarized here.
  3. A load or a door in the wind. Wind doesn't hit men. It hits the things men are standing next to.

Rain by itself does not stop work. Lightning, trench water, wind you have to brace against, and ice do. Knowing the difference is the whole skill.


2. LIGHTNING — THE 30/30 RULE

2.1 The count

2.2 Where everyone goes

2.3 The rig

2.4 The restart

2.5 If someone is struck


3. HIGH WIND

Wind has no flash-to-bang count, so the field test is honest and simple: if you have to brace against a gust, lifting and loading stop.


4. HEAVY RAIN

4.1 The trench — the one that kills

4.2 Locate paint washout

4.3 Working in the rain


5. COLD SNAP — GEORGIA VERSION

Georgia cold is a few mornings a year, which is exactly why it catches people.


6. WHO CALLS IT

NEVER — earned lines only


7. THE FIELD CARD (Tier 3 — laminate, one per truck)

NU-SAF-126-C — WEATHER CARD

LIGHTNING — 30/30 1. See flash → count seconds to thunder. 2. Under 30 = STOP. Everyone in cabs/trucks, windows up. 3. Not under trees. Not under the trailer. Not touching the rig. 4. Restart 30 min after LAST thunder. New rumble = clock resets. 5. WhatsApp your crew thread: WX STOP [site] [time] lightning / WX RESTART [time]. Affects another crew or the schedule? Also post it in NOVA — DISPATCH.

WIND - Brace test: gust makes you brace = lifting/loading stops. Land loads. - Latch trailer doors. Look UP for limbs. Blown cones = rebuild the zone (SAF-105) before work.

RAIN - Water in the trench = OUT of the trench. No re-entry until re-inspection (SAF-107). - Rain kills paint — re-verify locates (FLD-200 lunch check) before digging again.

ICE - Bridges freeze first. Slow before the bridge. - Dry gloves, three points of contact.

STRUCK BY LIGHTNING: 911, then CPR now — a strike victim is safe to touch.

WRITE IT: stop time, restart time, reason → DFR, same day.


8. PROOF & RECORDS (what has to exist when this is done right)

Every gate above lands on one of these records. The DFR weather entry is the Tier-4 record this document creates; the rest belong to the documents named.

8.1 DFR weather delay entry (Tier 4 — required fields)

Field What goes in it
Date / site / WO Standard DFR header
Weather stop time When the call was made
Restart time When work actually resumed
Reason Lightning / wind / rain-trench / rain-locates / ice
What was secured Loads landed, rig shut down, zone rebuilt, etc. — one line
Changed-conditions notice sent? Y/N — see 8.2

8.2 The record table

Record Who When Where it goes
Weather stop/restart entry (8.1) Crew Lead Same day, every stop DFR
Changed-conditions notice — any weather stop that costs schedule or footage the client is counting on Crew Lead → Supervisor Same day Per the Field Quality changed-conditions card (NU-QAL-600). A weather day the client hears about in the DFR three weeks later is a free delay claim against Nova. Same-day notice is what makes it billable or at least defensible. [Adam/counsel: confirm against the actual subcontract's weather/excusable-delay clause whether this changed-conditions notice satisfies it, or whether a separate weather-day notice format is required.]
Post-rain excavation re-inspection Competent person [unnamed — open on NU-GOV-000] Before any re-entry Inspection record per NU-SAF-107 [draft]
Locate re-verification after washout Crew Lead Before dig resumes Lunch-check line per NU-FLD-200
Strike-alert / locator function test after a nearby strike Operator Before boring resumes DFR note
WhatsApp WX STOP / RESTART messages Crew Lead or Supervisor At the stop and the restart Crew thread per NU-GOV-004

Accountability tie-in (NU-PPL-403): calling a weather stop = zero points, always. Working through a called stop, re-entering a wet trench ahead of inspection, or putting a man on the rig in a storm = [Adam: assign class — recommendation Class C, same family as working without a safety zone].


9. DONE WHEN


10. WHAT THIS DOCUMENT NEEDS FROM ADAM

  1. Set the Nova wind number (§3) — one company-wide stop threshold for lifting/loading, or confirm the brace test + manufacturer limit stands as the rule.
  2. Assign the points class for working through a called weather stop (§6, §8) — recommendation: Class C.
  3. Name the competent person for post-rain trench re-inspection — same open item as NU-SAF-107 and the NU-GOV-000 register, and this document can't fully operate until it's answered.
  4. Confirm the hydrovac freeze question (§5) — is there an overnight drain/freeze routine, and where should it live?
  5. Add the WX STOP / WX RESTART message format to the NU-GOV-004 WhatsApp templates so the card and the Daily Loop match.
  6. Add a weather module to the Day 1–2 training book — ten minutes on the 30/30 count and the card; the cheapest training block in the program.
  7. Confirm this document's parent element under NU-SAF-100 §5.
  8. DOT status: reactivate USDOT 4221697 (SAFER shows INACTIVE as of 8/1/26 — likely lapsed MCS-150). The 49 CFR 392.14 references in §3 and §5 are drafted as applying; the reactivation is an office task already open elsewhere and only noted here.
  9. Add the weather stop/restart/reason/secured/notice-sent fields (§8.1) to the Nova app (Softr) production-log schema so this gate is enforceable in the app, not just on paper.